喇 36 0注水站投产初期 ,共安装 6台DF2 5 0— 15 0× 11型注水泵 ,匹配电机为YK180 0— 2 / 990。正常生产时运行4台机组 ,同时靠打高压回流来控制注水压力和注水量 ,造成了注水能耗的巨大浪费。为了解决这一问题 ,1998年 8~ 9月份对该站 1# 机组进行了改造 ,重新组合运行机组 ,既满足了生产的需要 ,又达到了日节电 15 910kW·h ,年获效益 2 2 0 86万元的节能效果
La 36 0 injection station put into operation early, a total of 6 sets of DF2 5 0 - 15 0 × 11 type injection pump, matching motor YK180 0-2 / 990. The normal production of 4 units run at the same time by playing high pressure back to control the injection pressure and water injection volume, resulting in a huge waste of water injection energy consumption. In order to solve this problem, the No. 1 unit of this station was retrofitted from August to September 1998 to reorganize the operation units, which not only met the needs of production but also achieved 15 910kW · h of electricity saving per day and annual profit 2 2 0 860000 yuan energy-saving effect