我们的机械筑路队,主要是担任路基土方工程,有职工一百余人,配有80匹马力推土机十二台,平地机两台,实压机两台,汽车起重机一台,加油车一台,修理工程车三台,并配有民工100人担任辅助工作。两年来一直在海拔4000~5000米高原地区修筑公路路基。该地区空气稀薄,气候寒冷,人烟稀少,地质复杂。每年施工季节约七、八个月。1963年十台推土机做了1438个台班,完成土方39万方;1964年采用双班作业,十二台推土机做了2517个台班,完成
Our mechanical road construction team, mainly as a roadbed earthworks, a staff of more than 100 people, with 80 horsepower bulldozers twelve, two graders, two real presses, a truck crane, a fuel truck Taiwan, repair construction vehicles three, and with 100 migrant workers as ancillary work. Over the past two years has been at an altitude of 4000 ~ 5000 meters plateau road construction. The area is air thin, cold climate, sparsely populated, complex geology. The construction season each year about seven or eight months. In 1963 ten bulldozers made 1438 platform classes to complete 390,000 square earth; in 1964 the use of double-duty operation, dozens of dozer bulldozers 2517 classes completed