由中国统配煤矿总公司建筑安装工程公司第七工程处滑模攻关小组首创的复合壁结构同步现浇双滑新工艺,在1200万吨/年入洗能力的内蒙古准格尔黑岱沟露天煤矿选煤厂2个直径10米的联体矸石仓工程施工中获得成功。高度34.085M 的矸石仓原设计简壁和仓壁结构为C_(18)现浇混凝土厚200毫米,内外双层结构配筋,简壁和仓壁外侧设计有75毫米厚加气混凝土轻质砌块保温层,支托砌块的钢筋混凝土环状悬挑牛腿每隔3米一道,砌块外侧另有一层25毫米厚水泥砂浆抹灰层。设计单位采纳了施工意见,同意将轻质砌块修改为同厚度珍珠岩轻质混凝土进行二位一体同步现浇双滑施
Synchronous cast-in-situ double-slip new technology of composite wall structure pioneered by the Seventh Engineering Section of the China General Coal Mine Corporation Construction and Installation Engineering Co., Ltd., and 12 million tons/year washing capacity in Zhungeer Heidaigou, Inner Mongolia Two coal mine flume warehouses with a diameter of 10 meters were successfully constructed in the coal preparation plant. The height of 34.085M Fushikura original design simple wall and warehouse wall structure C_ (18) cast-in-place concrete thickness 200 mm, double and inner structure reinforcement, simple wall and warehouse wall design 75 mm thick aerated concrete lightweight building Block insulation layer, reinforced concrete ring cantilevered leg of the support block is every 3 meters, and there is a 25mm thick cement mortar plaster layer on the outside of the block. The design unit adopted the construction opinion and agreed to modify the lightweight blocks into the same thickness perlite light-weight concrete for simultaneous in-situ double-sliding