某热电厂3台发电机,装机总容量49MW。5台锅炉,锅炉总容量515t/h,锅炉排烟采用电除尘器除尘,每台锅炉1台电除尘器,每台电除尘器有3个电场,每个电场各1个积灰斗,每个灰斗底部装有1台除灰机。2003年某日下午,该电厂锅炉运行班组技术员李某,带领新工周某、陈某、陈某某,去处理该厂5号炉静电除尘器Ⅲ电场灰斗内积灰结块不下灰的故障,他们到现场打开除灰机的观察孔(灰斗东侧,孔内是除灰机的叶轮),并启动该电场除灰机。消除故障的工作就这样在技术
A thermal power plant 3 generators, installed capacity of 49MW. 5 boilers, the total capacity of the boiler 515t / h, the boiler exhaust dust with electrostatic precipitator, an electrostatic precipitator per boiler, each electric precipitator has three electric fields, each electric field a plot hopper, each ash Bottom of the bucket equipped with a Taiwan ash. One afternoon in 2003, the power plant boiler operation team technician Li, led the new work Zhou, Chen, Chen Moumou, to deal with the plant No. 5 electrostatic precipitator electrostatic precipitator dust within the ash bucket no less than gray cake Fault, they went to the scene to open the observation hole ash machine (east ash bucket, the hole is the impeller of the ash machine), and start the electric ash machine. Work to eliminate the fault is so technical