截止目前,河口村水库大坝坝体填筑至286米高程,实现大坝初期封顶;二期混凝土面板共计49仓,已完成19仓;累计完成投资4.4亿元,占其工程投资的88%。泄洪洞工程1#、2#进水塔封顶,导流洞下闸封堵,2#泄洪洞龙抬头改造边墙和顶拱共计15仓,已完成11仓,导流洞封堵段回填混凝土已浇筑完成90%;累计完成投资2.6亿元,占其工程投资的85%。溢洪道工程引渠段墙体及控制室段闸墩混凝土浇筑完成,泄槽段和挑流鼻坎段混凝土正在浇筑施工;累计完成投资1.0亿元,占其工程投资的77%。防渗工程已基本完工。2014年是河口村水库的攻坚年、冲刺年,计划于当年后汛期水库下闸蓄水,年底
Up to now, the dam of Hekou Village Reservoir dam is filled to an elevation of 286 meters to realize the initial capping of the dam. The second phase concrete baton has a total of 49 warehouses and 19 warehouses have been completed, with a total investment of 440 million yuan, accounting for 88% . Spillway tunnel project 1 #, 2 # intake towers capped, the diversion tunnel under the gate plugging, 2 # spillway tunnels and the top arch renovation of a total of 15 positions, has completed the 11 positions, the diversion tunnel sealing section backfill concrete Completed 90% has been pouring; total investment of 260 million yuan completed, accounting for 85% of its project investment. The spillway wall construction and control room pier pier concrete pouring completed, the spillway section and picks nose section of the concrete section is pouring construction; a total investment of 100000000 yuan, accounting for 77% of its project investment. Seepage control project has been basically completed. 2014 is a crucial year in the estuary reservoir, the sprint year, plans to flood the reservoir after the flood season, the end of the year