摘要:随着建筑业和建筑市场管理体制改革的不断深化及市场竞争日益的激烈,企业为了生存和发展,就必须编制一份具有竞争力的投标书。而投标书的编制分两个部分,一是技术部分,主要是指施工组织设计;二是商务部分,主要是投标报价,即工程造价。只有施工方案先进科学、投标报价合理的投标书,才具有竞争力。在这种情况下,施工企业应重视施工组织设计对工程造价的影响,为了中标,承揽更多的施工任务,需不断研究优化施工组织设计、合理确定工程造价的具体措施。以便充分利用企业现有的人力物力和财力,争取最大的经济效益。
关键词:施工组织设计;工程造价;定额
Abstract: with the deepening and market competition in construction industry and construction market management system reform is becoming increasingly fierce, the enterprise in order to survive and develop, it must make a competitive tender. But the tender is divided into two parts, one is the technical part, mainly refers to the construction organization design; the two is the business section, is mainly the bidding, the construction cost. Only the construction scheme of advanced scientific, reasonable tender bidding, is competitive. In this case, the construction enterprise should pay attention to the impact, the construction organization design of engineering cost in order to win the bid, undertake the construction task more, need to continue to study the optimization of construction organization design, rationally determine the specific measures of project cost. In order to make full use of the existing manpower and financial resources, to achieve maximum economic benefit.
Keywords: construction design; project cost; quota
中圖分类号: TU723.3文献标识码:A 文章编号:2095-2104(2013)
长期以来,我国建筑工程中工程造价控制很不得力,超投资的现象屡见不鲜,严重影响建筑工程的投资效益。随着社会主义市场经济的建立和不断地完善,建筑市场的竞争日趋异常激烈,客观形势对施工企业的要求,不仅仅在技术装备,人员素质,工期质量、施工组织等方面有较高的要求,而且对项目实施中的工程造价管理也有更高的要求。
施工组织设计是指导施工的一项技术经济性文件,是工程施工的技术纲领,是建筑工程设计与施工中的一项必不可少的内容。 它的先进性、适用性将直接关系到工程质量、安全、工期,最终将影响到工程项目的成本和效益。虽然在投标时施工企业一般都做了施工组织设计,并经过了建设单位的认可,但这种施工组织设计属于总的施工组织设计,对不同的单位工程未加以细分,不一定是最经济、最适用的。工程施工前,施工单位应调整、优化施工组织设计,对特殊施工方案进行经济技术比较,从中优化出技术先进、安全可靠、费用成本低、方便施工的最佳施工方案。在市场经济条件下,加强施工组织设计对降低工程造价的作用越来越明显。从工程本身的实际出发,施工组织设计的编制既要科学、合理,又要保证工程质量及工期,以达到降低工程造价的目的。
1、施工组织设计与工程造价的概念和任务
通常所说的施工组织设计,主要是指在项目实施阶段所进行的施工组织总设计和单位工程的施工组织设计,是指导工程投标、签订承包合同、施工准备和施工全过程的技术经济文件。施工组织设计既是以施工企业以实现高质、高效、低耗为目的,对拟建工程在人力和物力、时间和空间、技术和组织上作出的合理的安排,也是业主在评标中选择施工队伍的重要考核依据。施工组织设计作为项目管理的规划性文件,提出工程施工中进度控制、质量控制、成本控制、安全控制、现场管理、各项生产要素管理的目标及技术组织措施。它既解决施工技术问题、指导施工全过程,同时又要考虑到经济效果。它不断在施工管理中发挥作用,而且在经营管理和提高经济效益上发挥着作用。每一项施工组织设计,都是保证工程顺利进行、确保工程质量、有效地控制工程造价的重要工具。
工程造价,即建筑安装工程的价格,从工程承包的角度出发,是指工程承包单位、施工企业按照承包合同约定,完成施工任务,业主应当付给的工程款即建筑安装工程价款。工程造价的确定,是以施工组织设计为依据,并综合考虑企业现有的人力资源、施工设备的配备情况、施工任务的饱满情况等诸多因素。合理地确定工程造价,有效地控制工程投资,尽量做到少投入、多产出,使有限的资源得到合理的运用,以尽量少的劳动消耗取得较高的经济效益。
2、施工组织设计与工程造价的关系
施工组织设计是工程施工的技术纲领,它的先进性、适用性将直接关系到工程质量、安全、工期,最终将影响到工程项目的成本和效益。虽然在投标时施工企业一般都做了施工组织设计,并经过了建设单位的认可,但这种施工组织设计属于总的施工组织设计,对不同的单位工程未加以细分,不一定是最经济、最适用的。工程施工前,施工单位应调整、优化施工组织设计,对特殊施工方案进行经济技术比较,从中优化出技术先进、安全可靠、费用成本低、方便施工的最佳施工方案。
目前,在项目实施的各环节中,工程项目价格的确定一般经过施工图预算的编制、承包合同价的签订、工程结算价和工程决算价的确定等过程。而在上述价格形成过程中施工组织设计与工程造价的关系非常密切。施工组织设计与工程造价同等重要,但二者并非相互独立的,二者是密切联系,相互确定的关系。而工程造价是由施工组织设计确定,工程造价的高低除了与预算知识有关外,其实很大程度上取决于施工方案的先进与否,不同的施工方案所反映的价格是不一样的。只有根据合理的施工方案和施工技术,才能做出正确的工程单价,确定的工程造价才合理。而工程造价的合理确定同样影响着施工方案的优化。要做出一个合理的施工方案,施工技术人员还必须借助于工程概预算知识,如在施工布置、设计合理而施工方案不同的情况下,除方案本身的优劣外,工程造价计算准确与否将直接影响施工方案的优选。例如:就工程预算中基础单价与部分工程单价的确定,来探讨施工组织设计与工程造价之间相互确定的关系。
2.1基础单价
2.1.1材料预算单价
材料费一般占建安投资的60%左右。建筑工程中所用的外购材料如能选择合理的采购方案,将对保证施工进度、降低工程成本起到积极的作用。材料采购方案与运输方式的选择,必须以满足施工强度和有利于降低成本为原则,由施工组织设计分析比较确定。当材料采购方案一经确定,施工组织设计需进一步规划材料仓库的布置。材料仓库的布置以减少材料场内运输、减少材料场内二次转运,方便运输为原则。
2.1.2砂石料单价
工程中砂石料单价的高低,对工程造价有着较大影响,因此单价计算必须有可靠的地勘、试验资料。施工组织设计中对料场的规划、工艺流程的确定、加工系统的布置一定要合理、科学和先进。
2.2工程单价
概预算定额与施工组织设计是相互配套的,对于同一单项工程,如果采用不同施工方法,在概预算定额中就会有不同的人、材、机消耗与之呼应从而得出相应的项目单价。以土方工程为例,根据施工组织设计,选定土方开挖方法及运距,选用土方开挖机械设备的类型、容量及相配套的运输机械吨位,这些都确定后,即可套用相应的定额子目,从而算出土方开挖单价,不同容量挖掘机配备不同吨位的自卸汽车运输,单价是不相同的,这就需要工程预算的相关计算要看施工组织设计提供相关数据确定哪种方案比较经济合理,再结合施工企业机械设备装备情况,以提高机械的效率为目的选定最优的土方开挖施工方案。分析比较不同的施工方法,产生不同的单价,分析可知相同容量的挖掘机配不同吨位的自卸汽车运土,吨位大的自卸汽车土方单价高;同样吨位的自卸汽车配不同容量的挖掘机运土,容量大的挖掘机土方单价低,这涉及到一个机械设备是否配套、机械效率高低的问题。施工组织设计根据工程工期进度、施工条件来配备施工机械,工程造价的相关计算又为优化施工组织设计提供可靠依据。
由此可见工程项目的施工组织设计与其工程造价有着密切的关系。施工组织设计的基本内容有:工程概况和施工条件分析、主要工程的施工方案、施工进度计划和施工平面图。其中“施工方案”的确定,如:施工机械的选择水平运输和垂直运输方法的选择、主体结构的施工工艺等等,均直接影响着工程预、决算价格变化。在保证工程质量和满足工期的前提下,优化施工方案是控制和降低工程造价的重要措施。
3、强化施工组织设计有效地控制工程造价
在建筑工程中,施工组织设计是控制工程造价的重要环节。因此,应该重视施工组织设计的编制、审查工作。
(1)编制施工组织设计与预算定额相结合。预算定额具有“整体上的通用性和个体上的不相融性”的特性。在编制施工组织设计前,应该熟悉和掌握预算定额,并且要合理的应用预算定额。
(2)施工图预算的编制与施工组织设计编制应同步。施工图预算是指按照特定的施工方案和施工方法完成项目的施工所需的材料、人工、施工机械台班等预算价格编制和确定。而施工组织设计主要是为完成该项目施工而确定的施工方案和施工方法及施工工艺。一旦某个施工方法有变更,则施工图预算相应部分的价格也应随之而调整。总之,施工方案的变动将会影响到施工图预算中工程量和单价的变化,因此,施工图预算的编制与施工组织设计编制应同步进行,它们之间有着密不可分的关系,一个的变动将牵动着另一个的变动,所以它们要同步进行以便于控制工程造价。
一般来说,通过施工组织设计可以看到一个项目施工全过程的安排。因此,每一个施工企业都必须重视施工组织设计的编制工作,每一项目的业主也应重视施工组织没计的评审和监督。
作为一个施工企业,在项目投标,竞标中能否引起发包方的重视,除了自身的资质等级,实力、信誉等外,其主要因素还是取决于其报价是否合理,而恰如其分的报价又和施工组织设计的优劣密切相关。面对如此激烈的竞争的建筑市场,施工企业应根据拟建工程的现场条件、工程概况,进行周密的部署,认真研究各项技术指标、经济指标及有关组织措施、安全措施,确定合理的施工方案,使施工方案具有先进性,合理性、竞争性、适用性和可操作性。它既要考虑到业主方面的经济利益,同时也要考虑到施工企业方面的经济利益,真正的使项目在施工过程中达到高质量、低消耗的目的。
4、优化施工组织设计对合理确定工程造价的意义
(1)工组织设计的编制质量是合理确定工程造价的关键。施工组织设计编制质量的好坏是合理确定工程造价的關键,加强施工组织设计的编制质量对确定工程造价有很重要的作用。由于施工组织设计工作做得不够深入,对工程造价的确定带来很大的麻烦,同时也为合同的正常执行带来困难。因此,在施工组织设计的编制过程中,施工方案的选定不能简单地用行政命令的手段决定,而应当依靠集体的智慧,进行认真的比较讨论,从技术经济两个方面综合评定。
(2)优化施工组织设计是控制工程造价的基础。施工方案的设计是施工组织设计的中心环节,工程造价能否得到控制,同样取决于方案是否优良。在编制施工组织设计过程中,应对各种方案进行比较,在充分论证的基础上,从中选择最佳的设计方案,以合理确定工程造价。
(3)新技术、新工艺是降低工程造价的主要手段。在施工组织设计中应用新技术、新材料、新工艺、新设备,既可以提高生产效率,又可以降低工程造价。比如:碾压混凝土筑坝,大体积混凝土通仓浇筑及用土工布、土工膜代替土石坝反滤料等新技术、新材料、新工艺,即可加快施工进度,节省材料消耗,减少设备数量,又可降低工程造价。在施工组织设计中,应大力应用先进的技术和设备,为降低成本提供主要手段。
5、优化施工组织设计、合理确定工程造价的具体措施
优化施工组织设计、合理确定工程造价归根结底是工程造价管理的范畴,是经济与技术统一的管理过程。搞好施工组织设计是工程造价的一项重要内容,周密组织施工、施工方案优化、工期总进度计划安排、机械设备效率的提高、施工管理水平的提高从而使工程建设成本降低,所有这些都可以通过施工组织设计得以实现。具体的优化施工组织设计、合理确定工程造价的措施有:
(1)掌握准确的基础资料,熟悉定额涵盖的内容。
(2)要认真研究图纸及各种技术资料,对工程的每一部位都做到心中有数,在施工方案的确定时,应先比较施工方案的经济合理性,尽量选用较经济的施工方案,以达到控制工程造价的目的。
(3)要认真研究工期、质量、工艺三者之间的关系,根据企业自身的实际情况,采用新工艺、新设备、新材料,要因地制宜,靠加大企业自身的改革力度等措施来保证业主的工期和质量,要真正做到少投入、高效益,使施工组织设计不但在工期、质量、工艺上有一个突破性的进展,而且要为降低工程造价做出更大的贡献。
总之,提高造价人员的素质,使其既懂施工技术,又精通预算商务。在国外,作为一名造价工程师,必须具备15年以上的现场施工经验,对工程做出报价和提出施工案都由造价工程师独立完成,他们做出报价的理论是实物量法,根据公司的技术能力和自身施工经验做出各项内容所需费用的报价。目前,我国造价人员还达不到这样的素质,相信通过不断的努力和学习,我国造价人员的素质会得到不断的提高。最后,建议广大从事工程造价的工作者,能深入到生产第一线中去,借鉴国外先进的报价知识,为我国的造价事业做出贡献。
综上所述,施工组织设计与工程造价有着密切的关系,随着建筑业和建筑市场管理体制改革的不断深化及市场竞争日益的激烈,企业为了生存、发展和获得高利润应重视两者之间的关系,认真明确优化施工组织设计对工程造价的影响。在工程建设项目实施的各环节中,工程建设项目的价格确定一般经过施工图预算的编制,施工承包合同价款的确定,工程结算价和工程决算价的确定等过程。其中施工组织设计是影响工程造价的主要因素,因此,工程造价的管理,必须把施工组织设计作为重要环节抓紧抓好,在这方面应处理好两者的关系。为控制工程造价,取得良好地经济效益,应认真做好每一段工程的施工组织设计,以取得事半功倍的效果。
参考文献
[1]张一飞编著.施工组织设计是指导公路工程施工的重要内容.山西交通科技,2000
[2]张起森主编.公路施工组织及概预算(第二版).北京:人民交通出版社,1999
[3]胡兆同编著.工程进度监理.北京:人民交通出版社,1993
[4]廖正环主编.道路施工组织与管理.北京:人民交通出版社,1999
[5]马敬坤主编.公路施工组织设计.北京:人民交通出版社,2002
[6]陆春其主编.公路工程造价.北京人民交通出版社,2002
[7]严做人、孙立军.道路工程经济与管理.上海:同济大学出版社,1995
关键词:施工组织设计;工程造价;定额
Abstract: with the deepening and market competition in construction industry and construction market management system reform is becoming increasingly fierce, the enterprise in order to survive and develop, it must make a competitive tender. But the tender is divided into two parts, one is the technical part, mainly refers to the construction organization design; the two is the business section, is mainly the bidding, the construction cost. Only the construction scheme of advanced scientific, reasonable tender bidding, is competitive. In this case, the construction enterprise should pay attention to the impact, the construction organization design of engineering cost in order to win the bid, undertake the construction task more, need to continue to study the optimization of construction organization design, rationally determine the specific measures of project cost. In order to make full use of the existing manpower and financial resources, to achieve maximum economic benefit.
Keywords: construction design; project cost; quota
中圖分类号: TU723.3文献标识码:A 文章编号:2095-2104(2013)
长期以来,我国建筑工程中工程造价控制很不得力,超投资的现象屡见不鲜,严重影响建筑工程的投资效益。随着社会主义市场经济的建立和不断地完善,建筑市场的竞争日趋异常激烈,客观形势对施工企业的要求,不仅仅在技术装备,人员素质,工期质量、施工组织等方面有较高的要求,而且对项目实施中的工程造价管理也有更高的要求。
施工组织设计是指导施工的一项技术经济性文件,是工程施工的技术纲领,是建筑工程设计与施工中的一项必不可少的内容。 它的先进性、适用性将直接关系到工程质量、安全、工期,最终将影响到工程项目的成本和效益。虽然在投标时施工企业一般都做了施工组织设计,并经过了建设单位的认可,但这种施工组织设计属于总的施工组织设计,对不同的单位工程未加以细分,不一定是最经济、最适用的。工程施工前,施工单位应调整、优化施工组织设计,对特殊施工方案进行经济技术比较,从中优化出技术先进、安全可靠、费用成本低、方便施工的最佳施工方案。在市场经济条件下,加强施工组织设计对降低工程造价的作用越来越明显。从工程本身的实际出发,施工组织设计的编制既要科学、合理,又要保证工程质量及工期,以达到降低工程造价的目的。
1、施工组织设计与工程造价的概念和任务
通常所说的施工组织设计,主要是指在项目实施阶段所进行的施工组织总设计和单位工程的施工组织设计,是指导工程投标、签订承包合同、施工准备和施工全过程的技术经济文件。施工组织设计既是以施工企业以实现高质、高效、低耗为目的,对拟建工程在人力和物力、时间和空间、技术和组织上作出的合理的安排,也是业主在评标中选择施工队伍的重要考核依据。施工组织设计作为项目管理的规划性文件,提出工程施工中进度控制、质量控制、成本控制、安全控制、现场管理、各项生产要素管理的目标及技术组织措施。它既解决施工技术问题、指导施工全过程,同时又要考虑到经济效果。它不断在施工管理中发挥作用,而且在经营管理和提高经济效益上发挥着作用。每一项施工组织设计,都是保证工程顺利进行、确保工程质量、有效地控制工程造价的重要工具。
工程造价,即建筑安装工程的价格,从工程承包的角度出发,是指工程承包单位、施工企业按照承包合同约定,完成施工任务,业主应当付给的工程款即建筑安装工程价款。工程造价的确定,是以施工组织设计为依据,并综合考虑企业现有的人力资源、施工设备的配备情况、施工任务的饱满情况等诸多因素。合理地确定工程造价,有效地控制工程投资,尽量做到少投入、多产出,使有限的资源得到合理的运用,以尽量少的劳动消耗取得较高的经济效益。
2、施工组织设计与工程造价的关系
施工组织设计是工程施工的技术纲领,它的先进性、适用性将直接关系到工程质量、安全、工期,最终将影响到工程项目的成本和效益。虽然在投标时施工企业一般都做了施工组织设计,并经过了建设单位的认可,但这种施工组织设计属于总的施工组织设计,对不同的单位工程未加以细分,不一定是最经济、最适用的。工程施工前,施工单位应调整、优化施工组织设计,对特殊施工方案进行经济技术比较,从中优化出技术先进、安全可靠、费用成本低、方便施工的最佳施工方案。
目前,在项目实施的各环节中,工程项目价格的确定一般经过施工图预算的编制、承包合同价的签订、工程结算价和工程决算价的确定等过程。而在上述价格形成过程中施工组织设计与工程造价的关系非常密切。施工组织设计与工程造价同等重要,但二者并非相互独立的,二者是密切联系,相互确定的关系。而工程造价是由施工组织设计确定,工程造价的高低除了与预算知识有关外,其实很大程度上取决于施工方案的先进与否,不同的施工方案所反映的价格是不一样的。只有根据合理的施工方案和施工技术,才能做出正确的工程单价,确定的工程造价才合理。而工程造价的合理确定同样影响着施工方案的优化。要做出一个合理的施工方案,施工技术人员还必须借助于工程概预算知识,如在施工布置、设计合理而施工方案不同的情况下,除方案本身的优劣外,工程造价计算准确与否将直接影响施工方案的优选。例如:就工程预算中基础单价与部分工程单价的确定,来探讨施工组织设计与工程造价之间相互确定的关系。
2.1基础单价
2.1.1材料预算单价
材料费一般占建安投资的60%左右。建筑工程中所用的外购材料如能选择合理的采购方案,将对保证施工进度、降低工程成本起到积极的作用。材料采购方案与运输方式的选择,必须以满足施工强度和有利于降低成本为原则,由施工组织设计分析比较确定。当材料采购方案一经确定,施工组织设计需进一步规划材料仓库的布置。材料仓库的布置以减少材料场内运输、减少材料场内二次转运,方便运输为原则。
2.1.2砂石料单价
工程中砂石料单价的高低,对工程造价有着较大影响,因此单价计算必须有可靠的地勘、试验资料。施工组织设计中对料场的规划、工艺流程的确定、加工系统的布置一定要合理、科学和先进。
2.2工程单价
概预算定额与施工组织设计是相互配套的,对于同一单项工程,如果采用不同施工方法,在概预算定额中就会有不同的人、材、机消耗与之呼应从而得出相应的项目单价。以土方工程为例,根据施工组织设计,选定土方开挖方法及运距,选用土方开挖机械设备的类型、容量及相配套的运输机械吨位,这些都确定后,即可套用相应的定额子目,从而算出土方开挖单价,不同容量挖掘机配备不同吨位的自卸汽车运输,单价是不相同的,这就需要工程预算的相关计算要看施工组织设计提供相关数据确定哪种方案比较经济合理,再结合施工企业机械设备装备情况,以提高机械的效率为目的选定最优的土方开挖施工方案。分析比较不同的施工方法,产生不同的单价,分析可知相同容量的挖掘机配不同吨位的自卸汽车运土,吨位大的自卸汽车土方单价高;同样吨位的自卸汽车配不同容量的挖掘机运土,容量大的挖掘机土方单价低,这涉及到一个机械设备是否配套、机械效率高低的问题。施工组织设计根据工程工期进度、施工条件来配备施工机械,工程造价的相关计算又为优化施工组织设计提供可靠依据。
由此可见工程项目的施工组织设计与其工程造价有着密切的关系。施工组织设计的基本内容有:工程概况和施工条件分析、主要工程的施工方案、施工进度计划和施工平面图。其中“施工方案”的确定,如:施工机械的选择水平运输和垂直运输方法的选择、主体结构的施工工艺等等,均直接影响着工程预、决算价格变化。在保证工程质量和满足工期的前提下,优化施工方案是控制和降低工程造价的重要措施。
3、强化施工组织设计有效地控制工程造价
在建筑工程中,施工组织设计是控制工程造价的重要环节。因此,应该重视施工组织设计的编制、审查工作。
(1)编制施工组织设计与预算定额相结合。预算定额具有“整体上的通用性和个体上的不相融性”的特性。在编制施工组织设计前,应该熟悉和掌握预算定额,并且要合理的应用预算定额。
(2)施工图预算的编制与施工组织设计编制应同步。施工图预算是指按照特定的施工方案和施工方法完成项目的施工所需的材料、人工、施工机械台班等预算价格编制和确定。而施工组织设计主要是为完成该项目施工而确定的施工方案和施工方法及施工工艺。一旦某个施工方法有变更,则施工图预算相应部分的价格也应随之而调整。总之,施工方案的变动将会影响到施工图预算中工程量和单价的变化,因此,施工图预算的编制与施工组织设计编制应同步进行,它们之间有着密不可分的关系,一个的变动将牵动着另一个的变动,所以它们要同步进行以便于控制工程造价。
一般来说,通过施工组织设计可以看到一个项目施工全过程的安排。因此,每一个施工企业都必须重视施工组织设计的编制工作,每一项目的业主也应重视施工组织没计的评审和监督。
作为一个施工企业,在项目投标,竞标中能否引起发包方的重视,除了自身的资质等级,实力、信誉等外,其主要因素还是取决于其报价是否合理,而恰如其分的报价又和施工组织设计的优劣密切相关。面对如此激烈的竞争的建筑市场,施工企业应根据拟建工程的现场条件、工程概况,进行周密的部署,认真研究各项技术指标、经济指标及有关组织措施、安全措施,确定合理的施工方案,使施工方案具有先进性,合理性、竞争性、适用性和可操作性。它既要考虑到业主方面的经济利益,同时也要考虑到施工企业方面的经济利益,真正的使项目在施工过程中达到高质量、低消耗的目的。
4、优化施工组织设计对合理确定工程造价的意义
(1)工组织设计的编制质量是合理确定工程造价的关键。施工组织设计编制质量的好坏是合理确定工程造价的關键,加强施工组织设计的编制质量对确定工程造价有很重要的作用。由于施工组织设计工作做得不够深入,对工程造价的确定带来很大的麻烦,同时也为合同的正常执行带来困难。因此,在施工组织设计的编制过程中,施工方案的选定不能简单地用行政命令的手段决定,而应当依靠集体的智慧,进行认真的比较讨论,从技术经济两个方面综合评定。
(2)优化施工组织设计是控制工程造价的基础。施工方案的设计是施工组织设计的中心环节,工程造价能否得到控制,同样取决于方案是否优良。在编制施工组织设计过程中,应对各种方案进行比较,在充分论证的基础上,从中选择最佳的设计方案,以合理确定工程造价。
(3)新技术、新工艺是降低工程造价的主要手段。在施工组织设计中应用新技术、新材料、新工艺、新设备,既可以提高生产效率,又可以降低工程造价。比如:碾压混凝土筑坝,大体积混凝土通仓浇筑及用土工布、土工膜代替土石坝反滤料等新技术、新材料、新工艺,即可加快施工进度,节省材料消耗,减少设备数量,又可降低工程造价。在施工组织设计中,应大力应用先进的技术和设备,为降低成本提供主要手段。
5、优化施工组织设计、合理确定工程造价的具体措施
优化施工组织设计、合理确定工程造价归根结底是工程造价管理的范畴,是经济与技术统一的管理过程。搞好施工组织设计是工程造价的一项重要内容,周密组织施工、施工方案优化、工期总进度计划安排、机械设备效率的提高、施工管理水平的提高从而使工程建设成本降低,所有这些都可以通过施工组织设计得以实现。具体的优化施工组织设计、合理确定工程造价的措施有:
(1)掌握准确的基础资料,熟悉定额涵盖的内容。
(2)要认真研究图纸及各种技术资料,对工程的每一部位都做到心中有数,在施工方案的确定时,应先比较施工方案的经济合理性,尽量选用较经济的施工方案,以达到控制工程造价的目的。
(3)要认真研究工期、质量、工艺三者之间的关系,根据企业自身的实际情况,采用新工艺、新设备、新材料,要因地制宜,靠加大企业自身的改革力度等措施来保证业主的工期和质量,要真正做到少投入、高效益,使施工组织设计不但在工期、质量、工艺上有一个突破性的进展,而且要为降低工程造价做出更大的贡献。
总之,提高造价人员的素质,使其既懂施工技术,又精通预算商务。在国外,作为一名造价工程师,必须具备15年以上的现场施工经验,对工程做出报价和提出施工案都由造价工程师独立完成,他们做出报价的理论是实物量法,根据公司的技术能力和自身施工经验做出各项内容所需费用的报价。目前,我国造价人员还达不到这样的素质,相信通过不断的努力和学习,我国造价人员的素质会得到不断的提高。最后,建议广大从事工程造价的工作者,能深入到生产第一线中去,借鉴国外先进的报价知识,为我国的造价事业做出贡献。
综上所述,施工组织设计与工程造价有着密切的关系,随着建筑业和建筑市场管理体制改革的不断深化及市场竞争日益的激烈,企业为了生存、发展和获得高利润应重视两者之间的关系,认真明确优化施工组织设计对工程造价的影响。在工程建设项目实施的各环节中,工程建设项目的价格确定一般经过施工图预算的编制,施工承包合同价款的确定,工程结算价和工程决算价的确定等过程。其中施工组织设计是影响工程造价的主要因素,因此,工程造价的管理,必须把施工组织设计作为重要环节抓紧抓好,在这方面应处理好两者的关系。为控制工程造价,取得良好地经济效益,应认真做好每一段工程的施工组织设计,以取得事半功倍的效果。
参考文献
[1]张一飞编著.施工组织设计是指导公路工程施工的重要内容.山西交通科技,2000
[2]张起森主编.公路施工组织及概预算(第二版).北京:人民交通出版社,1999
[3]胡兆同编著.工程进度监理.北京:人民交通出版社,1993
[4]廖正环主编.道路施工组织与管理.北京:人民交通出版社,1999
[5]马敬坤主编.公路施工组织设计.北京:人民交通出版社,2002
[6]陆春其主编.公路工程造价.北京人民交通出版社,2002
[7]严做人、孙立军.道路工程经济与管理.上海:同济大学出版社,1995