据日本电源开发公司于1985年11月6日发布的消息称,土耳其水利局指定该公司承包波亚巴德凯皮斯水电站工程的施工设计。土耳其的需电量,过去10年平均的增长率为10%以上,截至1983年年底为止,该国的总装机容量约为690万kw。根据该国的远景发展规划,1994年的装机容量为2650万kw,约相当于当前装机容量的4倍,且1994年的能源构成,水电将占总装机容量的60%波亚巴德凯皮斯电站工程为该远景规划的一部分,于1992年投入运行。
According to the Japan Power Development Corporation released on November 6, 1985, the Turkish Water Resources Agency designated the company contracted for the design of the construction of the Kapadis Hydropower Station. Demand for electricity in Turkey, with an average growth rate of over 10% over the past 10 years, totaled about 6.9 million kw by the end of 1983. According to the country’s long-term development plan, the installed capacity in 1994 was 26.5 million kw, equivalent to about 4 times the current installed capacity, and the energy composition in 1994 would make up 60% of the total installed capacity. Po’Abad Kepi The power plant project was put into operation in 1992 as part of the long-term plan.