大孤山铁矿微差爆破延期时间的优化研究

来源 :矿业研究与开发 | 被引量 : 0次 | 上传用户:shiguzxy
下载到本地 , 更方便阅读
声明 : 本文档内容版权归属内容提供方 , 如果您对本文有版权争议 , 可与客服联系进行内容授权或下架
论文部分内容阅读
为确定大孤山铁矿微差爆破的合理微差延期时间,借助有限元软件ANSYS/LS-DYNA对双孔微差爆破进行二维数值计算。根据模拟计算结果,对大孤山铁矿铁矿石爆破推荐的合理微差延期时间为:若使用高精度非电导爆管雷管爆破,孔间和排间微差时间应分别为25ms和65ms;若使用数码电子雷管爆破,孔间和排间微差时间应分别为35ms和70ms;试验表明,利用推荐的延期时间进行爆破,可使爆堆块度更加均匀,提高了爆堆的松散性及电铲装车的效率。 In order to determine the reasonable time delay for the micro-scale blasting of Dagushan iron mine, two-dimensional numerical calculation of two-hole millisecond blasting was performed with finite element software ANSYS / LS-DYNA. According to the simulation results, the reasonably suitable delay time for iron ore blasting in Dagushan Iron Mine is as follows: if the use of high precision non-conductive tube detonator blasting, the time difference between holes and rows should be 25ms and 65ms respectively; If digital electronic detonator blasting is used, the time difference between holes and rows should be 35ms and 70ms respectively. The tests show that using the recommended detonation time to make blasting block more uniform and improve the looseness of the blasting pile and Electric shovel loading efficiency.
其他文献
在机械设备使用过程中,有时会出现这种现象:因轴承损坏或安装不正确导致轴头磨损,而轴的其他部位却完好无损。在某些情况下,因新轴总成购买相对较贵,而且不一定能够及时买到,
命运和机遇对他来说实在是公平的。过去 ,他和他的建筑队还是一个鲜为人知的“丑小鸭”。如今 ,他和他的建筑大军已是羽毛丰满的“白天鹅”。自称是“兵头将尾”的沈良兵 ,现
期刊
期刊
期刊
该文从挂篮荷载计算、施工流程、支座及临时固结施工、挂篮安装及试验、合拢段施工、模板制作安装、钢筋安装、混凝土的浇筑及养生、测量监控等方面人手,介绍了S226海滨大桥
期刊
汉民族是我国最庞大的主体民族,随着历史的发展,沉淀下了深厚而绚烂的服饰文化,中国汉族女性婚礼服是其中的核心部分,也是中国服装历史文化中的精髓。本课题客观的总结了古代汉民
该文从挂篮荷载计算、施工流程、支座及临时固结施工、挂篮安装及试验、合拢段施工、模板制作安装、钢筋安装、混凝土的浇筑及养生、测量监控等方面人手,介绍了S226海滨大桥