一、基本概况目前,在我国的基本建设中遇到的首要问题是资金紧张;与此同时,又存在着资金使用效率低、资金严重浪费的现象。特别是在一些大中型建设项目中,超概算已是普遍现象。因此,如何降低工程造价、提高投资效益是人们普遍关心的问题。衡水发电厂是国家和地方共同投资兴建的大型电厂,一期工程装机2×300MW,工程于1993年12月开工,二台机组分别于94年、95年投产发电。一期工程国家能源部电规[1993]178号文件批复工程总投资189795万元;调整后根据电规[1996]228号文件批复的概算289000万元;比原概算净增99205万元。其中:
I. Basic Facts At present, the primary problem encountered in capital construction in our country is the shortage of funds. At the same time, there is also a phenomenon of inefficient use of funds and serious waste of funds. Especially in some large and medium-sized construction projects, over budget estimates are a common phenomenon. Therefore, how to reduce construction cost and improve investment efficiency are the common concerns. Hengshui Power Plant is a large-scale power plant jointly invested by the country and the local government. The first phase of the project is 2 × 300MW. The project was started in December 1993 and the second unit was put into operation in 1994 and 1995 respectively. The first phase of the project, Ministry of Energy Electricity [1993] 178 document approved a total investment of 1897950000 yuan; adjusted according to electric regulation [1996] No. 228 document approval of 289000 yuan; a net increase of 992050000 yuan than the original estimate. among them: