上海浦东国际机场T1航站楼预留了供旅客捷运的地下通道,其中F1区为地下1层钢筋混凝土结构,深基坑占据大半施工场地,上部为新建3层钢筋混凝土结构。在结构施工与现场道路布置相互制约、几乎无路可走的情况下,通过优化基坑围护第1道混凝土支撑及压顶梁标高;设置临时立柱对6 m层永久结构进行支承,成功达到了利用场地东侧浅基础结构作为现场施工道路的目的。同时合理设置施工缝,解决了高大截面混凝土转换大梁的分步施工难题,既协调了深基坑和浅基础结构施工,又确保了不停航运营要求,加快了工程进度,节约了地下通道费70万元。
T1 terminal of Shanghai Pudong International Airport has reserved underground passage for passengers’ MRT. Among them, F1 area is underground reinforced concrete structure of 1 floor, deep foundation pit occupies most of the construction site, and the upper part is a new 3-story reinforced concrete structure. Under the condition that the structure construction and the on-the-spot road layout are restricted and hardly any feasible, the first concrete support and the crest beam elevation of the foundation pit support are optimized and the temporary column is used to support the 6 m-layer permanent structure, which successfully achieves Use the shallow foundation on the eastern side of the site as the site of construction road. At the same time, the construction joints are reasonably set up to solve the problem of the step-by-step construction of the large cross-section concrete conversion girder, which not only coordinates the construction of the deep foundation pit and the shallow foundation structure but also ensures the non-stop operation requirement, accelerates the construction progress and saves the underground passage fee 70 Million.