包钢白云铁矿工业锅炉房安装有4台 SZL10-13.5-AⅡ型锅炉,全部为1996年制造的快装链条炉,用于冬季供暖,其供暖面积约为18万 m~2,年消耗原煤约1.2万 t。给煤方法为煤经过破碎,由上煤带式输送机输送,经过各台炉的溜煤管、煤斗和煤闸板,进入炉膛燃烧为加强节能减排,2008年10月用20 d 时间对工业锅炉房给煤加装分层布煤装置进行
Baotou Iron & Steel Co., Ltd. installed 4 sets of SZL10-13.5-AⅡ boiler in the industrial boiler room of Baishan Iron and Steel Co., Ltd., all of them are quick-loading chain furnaces manufactured in 1996 for heating in winter. The heating area is about 180,000 m 2, About 12,000 t. The coal feeding method is that the coal is crushed and transported by the coal belt conveyor. After passing through the coal-feeding pipe, coal hopper and coal gate of each furnace, it enters the furnace for combustion. In October 2008, it takes 20 days The industrial boiler room to install coal feeding and stratification cloth