大型水电站发电机定子现场装配克服了分辨定子诸多缺陷,其优越性已被人们普遍认同并广泛采用.但在现场复杂环境条件下定子装配工艺要求更精、质量要求更高,同时装配工作量大,占用机组安装的直线工期长.本文就大朝山水电站225MW机组发电机定子现场装配为例,阐述如何针对定子结构的特点进行现场装配,以及在施工中如何采取有效措施对工艺、质量、进度进行控制,以保证定子装配高质量、高水平、高速度.此外还就加速装机进度作了简要探讨.
Large-scale hydropower station generator stator assembly to overcome the many problems of resolving the stator, the superiority has been widely recognized and widely used.But in complex field conditions of the stator assembly process requires more refined, higher quality requirements, while the assembly workload , Takes a long time to install the unit straight line.In this paper, the stator assembly of 225 MW unit of Dachaoshan Hydropower Station on site was taken as an example to illustrate how to carry out on-site assembly according to the characteristics of the stator structure and how to take effective measures in the construction process, quality, progress Control, to ensure the stator assembly of high quality, high level, high speed.In addition to speeding up the installation progress made a brief discussion.