论文部分内容阅读
苏丹东卡哈拉灌溉项目主泵站水泵房根据其地形地质条件并结合类似工程的设计施工经验等,对4种布置方案进行分析和论证,确定最优的布置方案,实施后提前了6个月工期,带来了相应的经济效益。
According to the topographic and geological conditions and the design and construction experience of similar projects, the pump house of the main pumping station of the East Kalhala Irrigation Project in Sudan analyzed and demonstrated the four kinds of layout plans and determined the optimal layout plan. Six days prior to the implementation Month period, has brought the corresponding economic benefits.